Abstract
A company is bidding on a large project that involves the removal of several layers of existing roofing down to a concrete structural deck, and instalaltion of a new roof system including tapered insulation. Due to the complexity of the job, it is estimated daily production figured per square is very low. Do you have any suggestions?
A company is bidding on a large project that involves the removal of several layers of existing roofing down to a concrete structural deck, and instalaltion of a new roof system including tapered insulation. Due to the complexity of the job, it is estimated daily production figured per square is very low. Do you have any suggestions?
Date
1/1994
1/1994
Author(s)
Mark Graham
Mark Graham
Page(s)
45
45
Keyword(s)
reroof; tapered insulation; temporary roof